Texas Data Center Pause After the 2026 Election: What Hinojosa's Pledge Means for the Global AI Supply Chain
Gina Hinojosa, Texas's governor-elect, has pledged to pause data center approvals until the Legislature passes new protections, and approvals are already on hold under Abbott's orders. A data center stuck in review can't break ground or power up on time, so orders for AI chips, servers, networking, power and cooling gear could ship later.
Kelvin Wang · · 15 min read
Key points
- Data center approvals in Texas are already paused under Abbott's orders; Hinojosa, who takes office on January 19, 2027, has pledged to keep them on hold until the Legislature passes protections.
- A data center that can't get permits or a grid connection powers up later, so orders across the chain, from GPUs and memory to servers, power and cooling gear, could ship later.
- Lawmakers have already filed bills, including a Senate bill to repeal the data center sales tax exemption that 23 of the Senate's 31 members and members-elect had signed by November 9.
- Dates to watch: ERCOT's audit reports by December 10, the PUCT meeting on December 17, and January 12 and 19, 2027.
By Wells Fargo’s count, 27% of the data center capacity planned in the US is in Texas 1. The hardware for those buildings comes from a chain that crosses several countries: US chip designers, chipmakers and memory makers in Taiwan and Korea, Taiwanese server and power-supply makers, and US and European electrical gear. The open questions are how long the hold Abbott started lasts and how much capacity it catches.
What happened in the Texas election?
Hinojosa, a Democrat, beat Republican incumbent Greg Abbott on November 3. The Associated Press called the race at 10:17 p.m. Central time (04:17 UTC on November 4), and Abbott conceded: “There are still votes to be counted, but mathematically, we are not going to be able to win this election” 2.
In the Texas Secretary of State’s unofficial results, last updated at 22:59 UTC on November 4 with all polling locations reporting, Hinojosa has 5,230,789 votes and Abbott 4,524,527, a gap of about 706,000 3. The state has not certified the result.
Democrat Vikki Goodwin also beat Lieutenant Governor Dan Patrick, which will make her the state Senate’s presiding officer. In the Texas Tribune’s preliminary count, Democrats would control the House 83 seats to 67 if current results hold, while Republicans keep the Senate 19 to 12. The Republican majority was expected to consider rules that limit Goodwin’s powers 4. Texas is heading for split government.
The 90th Legislature convenes at noon on January 12, 2027 (18:00 UTC), and Hinojosa takes office on January 19 5. Abbott is still governor for the session’s first week.
What has Hinojosa said about data centers?
- July 23, asking Abbott to act. In KXAN coverage her campaign reposted, she said: “I am calling on Greg Abbott to issue a moratorium on any new data centers with an emergency executive order” 6.
- Campaign page, her standing position. “We need an immediate moratorium on data centers to last until the legislature can meet to put in place real protections” 7.
- October 22, her clearest pledge. In a video on X: “When I am governor I will issue a moratorium — a ban — on all data center approvals until laws can be passed by the Legislature to protect Texans” 8.
- November 5, after the win. In a CNN interview reported by Reuters, she said, “We will have laws to protect Texans, and we need to stop what we are doing with data centers until we have those protections,” and that communities need “a seat at the table” 9.
Two things follow from those lines: the pause covers approvals, meaning permits and grid connections still being sought, and it lasts until the Legislature passes protections. None of her statements found through November 17 says which projects it covers, when it would start, or what she will do about data centers on her first day. Her victory speech stayed general: “The voters have delivered a mandate for change, and it is change they will get” 10.
What she wants from lawmakers: union hiring requirements for data center operators, protection for communities’ water, an end to the nondisclosure agreements data center companies use, and a push to ensure that Texans won’t pay more for electricity because of data centers 8. She also wants to end data center tax subsidies, saying the sales tax exemption on the electricity data centers use costs Texas more than $1 billion a year 11.
Are Texas data center approvals already paused?
Yes. Abbott paused them himself, with letters to state agencies.
-
August 3
Abbott asked the Public Utility Commission of Texas (PUCT) and grid operator ERCOT to audit "all data center projects currently advancing through ERCOT's interconnection process" [12].
His letter put ERCOT's interconnection requests at "over 474 GW of capacity", about 90% of it data centers. Grid connections for large data centers went on hold while the audit runs.
-
August 21
Utility Dive reported that ERCOT's large-load study will be late.
About 300 data centers of 75 MW or more are in the study. "We will not have the study done by April 9, 2027," said ERCOT's Chad Seely. Seventeen large loads with about 6.6 GW of peak demand had passed the stability assessment, but ERCOT had not approved their energization [13].
-
September 14
He told the Texas Water Development Board to penalize data centers that don't report their water use [14].
-
September 21
He told the Texas Commission on Environmental Quality (TCEQ) to stop issuing data center permits until the audits are done.
His letter says "no other state agency shall move forward with regulatory approvals related to data centers" [14].
The pause has not stopped every permit. FracTracker found seven emission-limit certifications that TCEQ’s database recorded as issued after September 21, plus eleven construction stormwater records 15. In October, after advocates pointed out approvals issued after the pause began, TCEQ shut down its electronic filing system 5.
The audit is still running. At ERCOT’s November 5 update to the PUCT, first-round responses from 257 developers (about 5,140 questions) had been reviewed, a shorter second round was expected, and the review was not yet complete. ERCOT plans to file two reports by December 10, and the PUCT takes them up at its December 17 open meeting, the earliest date the TCEQ pause could lift 5.
Gordon Johnson of GLJ Research told CBS News: “Texas already has a moratorium — Abbott built it. All the new governor has to do is keep it in place” 16.
What can she do on her own, and what needs the Legislature?
A Texas governor can direct state agencies by executive order, but those orders “lack the permanency of a state law because any future governor can rescind past executive orders” 17. They bind agencies, not lawmakers. Both of Abbott’s pauses are letters to agencies, so once sworn in she can issue the same instructions, or broader ones, and keep the pause running until the Legislature acts.
- Her data center asks need laws. Ending the tax breaks, union hiring terms and water protections all need legislation.
- She can name PUCT nominees early, but confirmation is the hurdle. Commissioners Patrick Rhode and Morgan Johnson are recess appointees the Senate has not confirmed, and Commissioner Hjaltman’s term expired on September 1, 2025 18. The Texas Constitution requires the governor to nominate each recess appointee, or another person, within the first 10 days of the session. That window opens under Abbott on January 12 and closes days after she takes office. If no one is nominated, the Senate may treat the recess appointee as nominated. Confirmation needs two-thirds of the senators present 5. The regular terms of Rhode and Kathleen Jackson end on September 1, 2027 18.
- A blanket permit halt may not hold. When Abbott ordered the permit pause, Adrian Shelley of Public Citizen said “TCEQ has said before they don’t have the authority to halt all permits for a given industry”, and Luke Metzger of Environment Texas said the measures with the most impact “really do require legislative approval” 19.
- She has promised a residential rate freeze. She says she would direct the PUCT to “freeze the rates residential customers pay until we have laws” that make data centers and other large users cover their own costs 18.
That leaves a gap: the audit could be treated as complete on December 17, but she is not sworn in until January 19. For that month, Abbott decides what follows the audit.
What have lawmakers filed so far?
Bill prefiling opened on November 9, and more than 1,260 bills had been filed by the end of the first day 5. Among them is SB 293 by Senate Finance Committee Chair Joan Huffman, a Houston Republican 20, which would repeal the sales tax exemptions for property used in data centers and large data center projects. Its House companions are HB 167, HB 408 and HB 681 21. As announced, SB 293 would end exemptions for new projects, end existing exemptions on its effective date, and deny applications still pending that day 22. Twenty-three of the Senate’s 31 members and members-elect had signed on by the evening of November 9, and the Comptroller now projects the exemption’s cost at $3.3 billion for 2028–29 23.
On November 4, Bernstein’s Gautam Chhugani wrote: “We would expect the data center pause to continue and any data center potential legislation to remain in gridlock” 24. Since then the tax-break repeal has drawn wide Senate support, but rules on permits, water and grid access have not been tested, nothing has passed, and the regular session runs to May 31, 2027 5.
How much data center capacity is waiting in Texas?
- Texas share of planned US data center gigawatts (Wells Fargo)
- 27%
- CNBC
- ERCOT interconnection requests in Abbott's August 3 letter, about 90% data centers
- 474 GW+
- Troutman Pepper Locke
- Peak demand of 17 large loads that passed ERCOT's stability check but await energization
- 6.6 GW
- Utility Dive
Georgia has 7% in Wells Fargo’s count 1. SemiAnalysis says Texas accounts for nearly 30% of the US data center capacity set to come online in 2028 25.
Some of the best-known projects:
| Project | Location | Planned size | Status (as of) |
|---|---|---|---|
| Stargate (OpenAI, Oracle; built by Crusoe) | Abilene | 1.2 GW | About 0.3 GW estimated in operation (April 2026) |
| Stargate (Vantage) | Shackelford County | 2 GW | Under construction, roofing on the first building (April 2026) |
| Stargate (SB Energy, SoftBank) | Milam County | 1.2 GW | Under construction, first building framed and roofed (April 2026) |
| Galaxy Helios (leased to CoreWeave) | Dickens County | 133 MW critical IT load in phase I | Phase I completion announced July 2026; phase II (260 MW) deliveries expected from the first half of 2027 |
Stargate sites: Epoch AI tracker, published April 17, 2026, updated April 23 [26]. Galaxy Helios: Galaxy's July 2026 announcement [27].
In a note reported by Bloomberg, Johnson wrote that “projects with power, permits and steel keep going”, while those with power but no state environmental permit face a 12- to 18-month slip, and he put about 13 GW of Texas capacity immediately at risk 25. StoneX analyst Cody Acree says projects that are financed, contracted or under construction don’t automatically fall through 28.
How does a Texas pause travel through the AI supply chain?
The chain runs in one direction: a hold on approvals can delay construction or energization, which could push back rack installations and the hardware shipments behind them. If projects already under way keep going, as Johnson and StoneX’s Acree expect, the hit would land on the next wave of orders rather than on what is already being built.
Every layer of the chain sells into those buildings. Each of these companies reports its data center or AI exposure in its own filings or investor releases. They are examples of where the exposure sits, not stock picks.
- Chips and memory. Nvidia’s Data Center revenue was $107.6 billion of $115.8 billion in the quarter to October 25, reported on November 17 29. AMD’s Data Center segment brought in $8.5 billion of $13.4 billion 30, Broadcom’s AI semiconductors $16.7 billion of $29.6 billion 31, and TSMC’s high-performance computing platform 68% of its revenue 32. Micron’s Cloud Memory and Core Data Center units together made $34.3 billion of $54.2 billion 33. SK hynix says that in NAND, “high-value-added products for data centers continued to grow across the board” 34, and Samsung “significantly scaled up sales of HBM4” while server SSD demand grew 35.
- Servers, racks and chassis. At Foxconn, cloud and networking products passed 50% of revenue for the first time in the second quarter 36, and its chairman says “AI servers have become Foxconn’s most significant growth engine” 37. Wiwynn says “recent demand from data centers remains strong” 38. Dell reported $16.4 billion of AI-optimized server revenue out of $47.0 billion and ended the quarter with a $95 billion backlog 39. Chenbro calls itself “a leading professional server chassis manufacturer” 40.
- Networking. Cisco raised its expectation for AI infrastructure revenue from hyperscalers to $9 billion in fiscal 2027 41.
- Power and cooling. Delta Electronics says its AI data center businesses account for about 50% of revenue 42, and Lite-On puts AI-related revenue at more than 30% this year 43. Vertiv says “a substantial portion of our business depends on the continued growth” of its customers’ data centers 44, and Schneider Electric attributes 30% of its FY2025 orders to data centers and networks 45.
- Grid and generation. GE Vernova’s gas power backlog and slot reservations grew from 116 to 122 GW, with new products for “utility and data center customers” 46. Quanta Services, the grid contractor, points to “increasing demand for electricity associated with, among other things, data centers” 47.
Definitions differ by company. Calculated shares divide reported segment revenue by total revenue: Nvidia $107.6bn of $115.8bn (quarter to October 25, 2026); AMD $8.5bn of $13.4bn (third quarter 2026); Micron $34.3bn of $54.2bn (fiscal fourth quarter 2026); Broadcom $16.7bn of $29.6bn (fiscal third quarter 2026); Dell $16.4bn of $47.0bn (fiscal second quarter 2027). TSMC and Delta: third quarter 2026; Lite-On: 2026 to date (reported October 30); Foxconn: second quarter 2026.
Source: sec.gov, tsmc.com, honhai.com, deltaww.com, liteon.com
None of these companies says a Texas pause has cut its orders. A high share means a company sells a lot into data centers everywhere, not that its orders are in Texas.
What do the suppliers themselves say?
Two Taiwanese suppliers have named the risk. On its October 29 earnings call, Delta Electronics listed four constraints on data center construction. One was political: “Local opposition to data center projects and potential changes in state and local policies could complicate site selection and construction timelines, despite continued federal support.” It also said third-quarter revenue came in “slightly below expectations due to component shortages, supply chain mismatches, and delays in data center construction” 42.
Wiwynn, reporting on November 9, said it “will continue to closely monitor the potential policy implications of the U.S. midterm election results for data centers and carefully assess their potential impact on the industry” 38.
Are the plants that build AI hardware in Texas covered?
Several suppliers make hardware in Texas. Nvidia said in April 2025 that it was building supercomputer plants “with Foxconn in Houston and with Wistron in Dallas” 48. Wiwynn opened a manufacturing plant in Socorro, in El Paso County, on September 14 49, and Samsung expects operations at its new chip fab in Taylor to begin adding foundry capacity in 2027 35.
These are factories, not data centers. Hinojosa’s pledge is about data center approvals, and no source says manufacturing plants fall under it. Newtalk notes that the restrictions target new data centers, not server manufacturing 50.
How did markets react?
Newtalk reported these moves in Taipei at 01:47 UTC on November 5 (9:47 a.m. in Taipei) 50:
Newtalk adds that part of the decline may reflect a broader pullback in tech stocks.
Source: newtalk.tw
Elsewhere:
- US: CoreWeave and IREN fell 4% in morning trading. CNBC reported the early drop on November 4, with Nvidia slightly lower 1; IREN ended the day down 11.2% 51.
- US memory: Micron and SanDisk fell more than 7%. Cnyes reported the November 4 drops, with SK hynix’s US-listed shares down more than 5% 28.
- Korea and Taiwan: Samsung and SK hynix fell as much as 4%. Bloomberg reported the Seoul moves and said TSMC also slid 25.
What analysts said:
- Wells Fargo saw a tail risk. Ahead of the result, Ohsung Kwon wrote that “a Dem win could potentially be a left-tail event to the AI trade” 1.
- Goldman Sachs sized the policy risk. Its economists estimate that Democratic wins at the state and local level could bring short-term development pauses affecting about 45% of planned US build-out capacity, which does not mean those projects are frozen 28.
- Jefferies flagged a downgrade for Texas. It wrote before the election that a Hinojosa win “would result in an immediate statewide pause and move Texas from Tier 3 to Tier 4” on its political-risk framework 25.
- Elon Musk pointed to space. “Data centers in space looking pretty appealing right now,” he posted on X 1.
Why are bitcoin miners exposed too?
Bitcoin miners that have turned into AI data center developers are exposed too. Bernstein says more than half the power capacity held or planned by the miners-turned-AI developers it covers is in Texas, with IREN, Riot and Cipher the most exposed, and it cut price targets on seven miners by roughly 35% to 54% 24.
Source: equibles.com
Equibles lists those moves for November 4 and notes that Riot’s existing capacity is energized and not subject to the ERCOT audit 51. Crypto.news writes that her stated proposal concerns new data centers and does not announce a blanket ban on bitcoin mining or order existing sites to close 52. Hinojosa has not specified how her proposed moratorium would treat mining-only sites.
What dates should you watch?
-
December 10
ERCOT files its two audit reports. [5]
-
December 17
The PUCT takes up the reports at an open meeting.
The earliest date the TCEQ permit pause could lift. Abbott is still governor and decides what follows [5].
-
January 12, 2027
The 90th Legislature convenes at noon Central time (18:00 UTC). [5]
-
Around January 21, 2027
The 10-day window to nominate PUCT recess appointees closes. [5]
-
March 12, 2027
Last day to file bills. [5]
-
May 31, 2027
The regular session ends.
A nominee the Senate has not acted on by then is considered rejected. [5]
-
September 1, 2027
Two PUCT commissioners' regular terms end [18].
The pause she pledged is meant to run until lawmakers act. The longer that takes, the longer orders for Texas sites could wait, at every layer of the chain from GPUs and memory to Taiwanese racks and to power and cooling gear. None of this is investment advice.
Sources
- 1. CNBC: AI stocks and the Texas governor race
- 2. KUT: Texas governor election results
- 3. Texas Secretary of State: unofficial election results
- 4. Texas Tribune: Texas House and Senate outcomes
- 5. Gibson Dunn: Texas data center critical dates and procedures following the 2026 elections
- 6. Hinojosa campaign: call for a data center moratorium until the Legislature convenes
- 7. Hinojosa campaign: data centers priority page
- 8. Texas Tribune: what Hinojosa's win means for data centers
- 9. Reuters via Yahoo News: Texas governor-elect says state will have laws to shield citizens from data centers
- 10. Yahoo Finance: Democrats' victories in Texas laid bare voter unease over data centers
- 11. KPRC: Gina Hinojosa's plans for $1,500 checks, data centers and Medicaid
- 12. Troutman Pepper Locke: Texas hits pause on data center grid connections
- 13. Utility Dive: ERCOT and the PUCT data center audit
- 14. Texas Tribune: Abbott halts data center permits
- 15. FracTracker: Texas data center permits after the governor's halt
- 16. CBS News: midterm results and the data center buildout
- 17. Texas Tribune: what power a Texas governor holds
- 18. Troutman Pepper Locke: Texas election may reshape the PUCT
- 19. San Antonio Current: experts question Abbott's authority to pause data center permits
- 20. Texas Senate: Senator Joan Huffman, District 17
- 21. Texas Legislature Online: SB 293 bill history
- 22. Senator Joan Huffman Files Legislation to Repeal Data Center Sales Tax Exemptions
- 23. Foley & Lardner: Texas lawmakers file to repeal the data center sales tax exemption
- 24. CoinDesk: Wall Street cuts bitcoin miner price targets after Texas result
- 25. Bloomberg via Yahoo Finance: AI data center boom is set for upheaval after US election rout
- 26. Epoch AI: OpenAI Stargate, where the US sites stand
- 27. Fox34: Galaxy completes phase I of its Helios data center campus
- 28. Cnyes (in Chinese): memory stocks, Goldman and StoneX on the Texas result
- 29. Nvidia: Q3 fiscal 2027 results (SEC filing)
- 30. AMD: Q3 2026 results (SEC filing)
- 31. Broadcom: Q3 fiscal 2026 results (SEC filing)
- 32. TSMC: 3Q26 management report
- 33. Micron: fiscal Q4 2026 results (SEC filing)
- 34. SK hynix: Q3 2026 business results
- 35. Samsung Electronics: third quarter 2026 results
- 36. Hon Hai (Foxconn): 2Q26 results call transcript
- 37. Foxconn: 3Q26 results press release
- 38. Wiwynn: third quarter 2026 financial results
- 39. Dell Technologies: Q2 fiscal 2027 results (SEC filing)
- 40. Chenbro: AI rack-level solutions at OCP Global Summit 2026
- 41. Cisco: Q1 fiscal 2027 results (SEC filing)
- 42. Delta Electronics: 3Q26 earnings conference transcript
- 43. Lite-On: third quarter 2026 results
- 44. Vertiv: 2025 annual report on Form 10-K
- 45. Schneider Electric: FY2025 results presentation
- 46. GE Vernova: Q3 2026 results (SEC filing)
- 47. Quanta Services: Q3 2026 Form 10-Q
- 48. Nvidia: NVIDIA to manufacture American-made AI supercomputers in the US
- 49. Wiwynn: grand opening of advanced manufacturing facility in Texas
- 50. Newtalk (in Chinese): Taiwan server stocks after the Texas result
- 51. Equibles: Texas data center moratorium, which stocks are exposed
- 52. crypto.news: Cipher shares fall after the Texas governor election